According to the latest calculations, the Trans Mountain pipeline expansion project, which the Trudeau government purchased from Kinder Morgan in 2018, will cost $3.1 billion more than the $30.9 billion projected last May, bringing the total cost to about $34 billion — more than six times the original estimate.

Subscribe now to read the latest news in your city and across Canada.

Subscribe now to read the latest news in your city and across Canada.

Create an account or sign in to continue with your reading experience.

Don't have an account? Create Account

This is yet another setback for a project facing rising costs and delays. To understand how we arrived at this point, let’s trace the project’s history.

In 2013, Kinder Morgan applied to the National Energy Board (NEB) to essentially twin the existing pipeline built in 1953, which runs for 150 kilometres between Strathcona County, Alta., and Burnaby, B.C., intending to have oil flow through the expansion by December 2019.

In 2016, after three years of deliberations, the NEB approved the pipeline, subject to 157 conditions. By that time, according to Kinder Morgan, costs had risen by $2 billion, bringing the total cost to $7.4 billion.

And yet, despite Kinder Morgan following the legal and regulatory process to get the necessary approvals, the B.C. NDP and Green Party vowed to “immediately employ every tool available” to stop the project. At the same time, the Trudeau government was planning regulations that would increase the cost and uncertainty of infrastructure projects across the country.

Your noon-hour look at what's happening in Toronto and beyond.

By signing up you consent to receive the above newsletter from Postmedia Network Inc.

A welcome email is on its way. If you don't see it, please check your junk folder.

The next issue of Your Midday Sun will soon be in your inbox.

We encountered an issue signing you up. Please try again

Faced with mounting uncertainty and potential setbacks, Kinder Morgan planned to withdraw from the project in 2018. In response, the Trudeau government intervened, nationalizing the project by purchasing it from Kinder Morgan with taxpayer dollars for $4.5 billion. Once under government control, costs skyrocketed to $12.6 billion by 2020 and $21.4 billion by 2022 reportedly due to project safety requirements, financing costs, permitting costs, and crucially, more agreements with Indigenous communities. One year later, in 2023, the Trudeau government said the cost had risen to $30.9 billion.

To recap, since the Trudeau government purchased the project from Kinder Morgan for $4.5 billion in 2018, the cost of the Trans Mountain expansion has ballooned (in nominal terms) to $34 billion.

Surprised? You shouldn’t be.

When government attempts to build infrastructure projects, it often incurs cost overruns and delays due to a lack of incentives to build in an efficient and resourceful way. According to a study by Bent Flyvbjerg, an expert in this field, a staggering 90% of 258 public transportation projects (in 20 countries) exceeded their budgets. The reason behind this phenomenon is clear — unlike private enterprises, government officials can shift cost overruns onto the public without bearing any personal financial consequences.

And the Trudeau government continues to make a bad situation even worse by introducing uncertainty and erecting barriers to private-sector investment in vital infrastructure projects including pipelines. Federal Bill C-69, for instance, overhauled the entire environmental assessment process and imposed complex and subjective review requirements on major energy projects, casting doubt on the viability of future endeavours.

What’s the solution to this mess?

Clearly, if policymakers want to help develop Canada’s natural resource potential — and the jobs, economic opportunity and government revenue that comes with it — they must enact regulatory reform and incentivize private investment. Rather than assuming the role of construction companies, governments should create an environment conducive to private-sector participation, thereby mitigating risk to taxpayers.

By implementing reasonable and competitive regulations that enhance investment incentives, policymakers — including in the Trudeau government — can encourage the private sector to build large-scale infrastructure projects that benefit the Canadian economy.

Julio Mejia and Elmira Aliakbari are analysts at the Fraser Institute

Postmedia is committed to maintaining a lively but civil forum for discussion. Please keep comments relevant and respectful. Comments may take up to an hour to appear on the site. You will receive an email if there is a reply to your comment, an update to a thread you follow or if a user you follow comments. Visit our Community Guidelines for more information.

QOSHE - MEJIA & ALIAKBARI: Trans Mountain pipeline’s soaring cost proof of government failure - Julio Mejia
menu_open
Columnists Actual . Favourites . Archive
We use cookies to provide some features and experiences in QOSHE

More information  .  Close
Aa Aa Aa
- A +

MEJIA & ALIAKBARI: Trans Mountain pipeline’s soaring cost proof of government failure

6 0
20.03.2024

According to the latest calculations, the Trans Mountain pipeline expansion project, which the Trudeau government purchased from Kinder Morgan in 2018, will cost $3.1 billion more than the $30.9 billion projected last May, bringing the total cost to about $34 billion — more than six times the original estimate.

Subscribe now to read the latest news in your city and across Canada.

Subscribe now to read the latest news in your city and across Canada.

Create an account or sign in to continue with your reading experience.

Don't have an account? Create Account

This is yet another setback for a project facing rising costs and delays. To understand how we arrived at this point, let’s trace the project’s history.

In 2013, Kinder Morgan applied to the National Energy Board (NEB) to essentially twin the existing pipeline built in 1953, which runs for 150 kilometres between Strathcona County, Alta., and Burnaby, B.C., intending to have oil flow through the expansion by December 2019.

In 2016, after three years of deliberations, the NEB approved the pipeline, subject to 157 conditions. By that time, according to Kinder Morgan, costs had risen by $2 billion, bringing the total cost to........